EXIN
PR2F · Question #523
Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?
The correct answer is C. Senior Supplier. See the full explanation below for the reasoning.
Question
Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?
Options
- ATeam Manager
- BProject Manager
- CSenior Supplier
- DTeam member
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C76% (16)
- D14% (3)
Community Discussion