Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?

The correct answer is C. Senior Supplier. See the full explanation below for the reasoning.

Question

Which PRINCE2 role has a specific responsibility for briefing non-technical management on supplier aspects of the project?

Options

  • ATeam Manager
  • BProject Manager
  • CSenior Supplier
  • DTeam member

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    76% (16)
  • D
    14% (3)