Which PRINCE2 role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?
The correct answer is C. Project Assurance. See the full explanation below for the reasoning.
Question
Which PRINCE2 role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?
Options
- AProject Manager
- BExecutive
- CProject Assurance
- DQuality Assurance
How the community answered
(56 responses)- A2% (1)
- B9% (5)
- C84% (47)
- D5% (3)
Community Discussion