EXIN
PR2F · Question #518
Which is a specific responsibility of Project Assurance?
The correct answer is D. Checking the right people are being involved in writing product descriptions. See the full explanation below for the reasoning.
Question
Which is a specific responsibility of Project Assurance?
Options
- AApproving the Risk Management Strategy
- BGiving ad-hoc direction to the Project Manager
- CReporting highlights to the Project Board
- DChecking the right people are being involved in writing product descriptions
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C8% (2)
- D85% (22)
Community Discussion
No community discussion yet for this question.