Whose responsibility is it to assure the project's stakeholders that the project remains desirable, viable and achievable at all times?
The correct answer is D. Executive. See the full explanation below for the reasoning.
Question
Whose responsibility is it to assure the project's stakeholders that the project remains desirable, viable and achievable at all times?
Options
- AProject Manager
- BCorporate or programme management
- CSenior User
- DExecutive
How the community answered
(40 responses)- A15% (6)
- B3% (1)
- C8% (3)
- D75% (30)