PR2F · Question #507
User and Supplier are two of the three primary stakeholder interests that must be represented on the Project Board at all times. What is the third interest?
The correct answer is B. Business. See the full explanation below for the reasoning.
Question
User and Supplier are two of the three primary stakeholder interests that must be represented on the Project Board at all times. What is the third interest?
Options
- ACustomer
- BBusiness
- CProgramme
- DCorporate
How the community answered
(47 responses)- A13% (6)
- B74% (35)
- C9% (4)
- D4% (2)