nerdexam
EXIN

PR2F · Question #5

If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?

The correct answer is C. Raise an issue. See the full explanation below for the reasoning.

Question

If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?

Options

  • ARaise an Exception Report
  • BIssue an Exception Plan
  • CRaise an issue
  • DRaise a risk

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    4% (1)
  • C
    76% (19)
  • D
    8% (2)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice