PR2F · Question #5
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?
The correct answer is C. Raise an issue. See the full explanation below for the reasoning.
Question
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform the Project Manager?
Options
- ARaise an Exception Report
- BIssue an Exception Plan
- CRaise an issue
- DRaise a risk
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- C76% (19)
- D8% (2)