PR2F · Question #498

Which of the following best defines a project output?

The correct answer is D. Any one of the project's specialist products. See the full explanation below for the reasoning.

Question

Which of the following best defines a project output?

Options

  • AThe information required for decision-making purposes
  • BThe measurable improvement resulting from an outcome
  • CThe result of the change derived from using the project's outputs
  • DAny one of the project's specialist products

How the community answered

(44 responses)
  • A
    2% (1)
  • B
    11% (5)
  • C
    5% (2)
  • D
    82% (36)