Which of the following best defines a project output?
The correct answer is D. Any one of the project's specialist products. See the full explanation below for the reasoning.
Question
Which of the following best defines a project output?
Options
- AThe information required for decision-making purposes
- BThe measurable improvement resulting from an outcome
- CThe result of the change derived from using the project's outputs
- DAny one of the project's specialist products
How the community answered
(44 responses)- A2% (1)
- B11% (5)
- C5% (2)
- D82% (36)
Community Discussion