EXIN
PR2F · Question #496
A project being output oriented supports which PRINCE2 principle?
The correct answer is A. Focus on products. See the full explanation below for the reasoning.
Question
A project being output oriented supports which PRINCE2 principle?
Options
- AFocus on products
- BDefined roles and responsibilities
- CManage by stages
- DContinued business justification
How the community answered
(40 responses)- A75% (30)
- B8% (3)
- C3% (1)
- D15% (6)
Community Discussion