EXIN
PR2F · Question #460
If, for whatever reason, the business justification disappears once the project is underway, what does PRINCE2 suggest should happen?
The correct answer is C. The project should be stopped or changed. See the full explanation below for the reasoning.
Question
If, for whatever reason, the business justification disappears once the project is underway, what does PRINCE2 suggest should happen?
Options
- AThe project should continue until the next end stage assessment
- BA benefits review should be undertaken
- CThe project should be stopped or changed
- DAn exception assessment should be held to approve an Exception Plan to recover from the
How the community answered
(37 responses)- A5% (2)
- B3% (1)
- C81% (30)
- D11% (4)
Community Discussion
No community discussion yet for this question.