EXIN
PR2F · Question #457
Any project outcomes perceived as negative by one or more stakeholders would be documented in which product?
The correct answer is C. Business Case. See the full explanation below for the reasoning.
Question
Any project outcomes perceived as negative by one or more stakeholders would be documented in which product?
Options
- ARisk Management Strategy
- BIssue Register
- CBusiness Case
- DProject Product Description
How the community answered
(21 responses)- A5% (1)
- B10% (2)
- C81% (17)
- D5% (1)
Community Discussion