Which of the following statements is FALSE? PRINCE2 provides projects with . . .

The correct answer is C. Regular progress meetings throughout the project. See the full explanation below for the reasoning.

Question

Which of the following statements is FALSE? PRINCE2 provides projects with . . .

Options

  • AThe explicit recognition of project responsibilities
  • BA thorough but economical structure of reports
  • CRegular progress meetings throughout the project
  • DPlans designed to meet the needs of the different levels in the management team

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    11% (4)
  • C
    78% (28)
  • D
    8% (3)