PR2F · Question #418

Which of the following is a TRUE principle of a PRINCE2 project?

The correct answer is B. Work Package level activities are identified during Starting up a Project. See the full explanation below for the reasoning.

Question

Which of the following is a TRUE principle of a PRINCE2 project?

Options

  • APlease refer to section 2.3 in the PRINCE2 Manual
  • BWork Package level activities are identified during Starting up a Project
  • CA project has defined and agreed roles and responsibilities
  • DEvery project will need a different project management approach

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    82% (41)
  • C
    4% (2)
  • D
    12% (6)

Community Discussion

No community discussion yet for this question.