PR2F · Question #410
Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
The correct answer is D. Manage by stages. See the full explanation below for the reasoning.
Question
Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
Options
- AContinued business justification
- BManage by exception
- CFocus on products
- DManage by stages
How the community answered
(22 responses)- A9% (2)
- B5% (1)
- C5% (1)
- D82% (18)