When authorizing a stage, in which product would the Project Board look for an explanation of any deviations from the approved plans that are within tolerance?

The correct answer is B. End Stage Report. See the full explanation below for the reasoning.

Question

When authorizing a stage, in which product would the Project Board look for an explanation of any deviations from the approved plans that are within tolerance?

Options

  • ALessons Report
  • BEnd Stage Report
  • CBenefits Review Plan
  • DProject Initiation Documentation

How the community answered

(47 responses)
  • A
    13% (6)
  • B
    74% (35)
  • C
    9% (4)
  • D
    4% (2)