What role is responsible for creating a Team Plan in the Managing Product Delivery process?

The correct answer is B. Team Manager. See the full explanation below for the reasoning.

Question

What role is responsible for creating a Team Plan in the Managing Product Delivery process?

Options

  • AProject Manager
  • BTeam Manager
  • CProject Support
  • DSenior User

How the community answered

(54 responses)
  • A
    13% (7)
  • B
    78% (42)
  • C
    4% (2)
  • D
    6% (3)