PR2F · Question #386
What is the trigger for the Starting up a Project process?
The correct answer is C. Project mandate. See the full explanation below for the reasoning.
Question
What is the trigger for the Starting up a Project process?
Options
- AProject Brief
- BProject Plan
- CProject mandate
- DOutline Business Case
How the community answered