PR2F · Question #384

In what plan should project closure activities be planned?

The correct answer is B. Stage Plan for the final management stage. See the full explanation below for the reasoning.

Question

In what plan should project closure activities be planned?

Options

  • AClosure Stage Plan
  • BStage Plan for the final management stage
  • CInitiation Stage Plan
  • DTeam Plan

How the community answered

(30 responses)
  • A
    17% (5)
  • B
    70% (21)
  • C
    10% (3)
  • D
    3% (1)