nerdexam
EXIN

PR2F · Question #377

Which integrated element is described as being the guiding obligations and good practices which determine whether the project is genuinely using PRINCE2?

The correct answer is A. Principles. See the full explanation below for the reasoning.

Question

Which integrated element is described as being the guiding obligations and good practices which determine whether the project is genuinely using PRINCE2?

Options

  • APrinciples
  • BProcesses
  • CThemes
  • DTailoring PRINCE2 to the project environment

How the community answered

(41 responses)
  • A
    85% (35)
  • B
    10% (4)
  • C
    2% (1)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice