Which of the following would be done once the Project Board have authorized initiation?

The correct answer is B. Establish who needs information, when and in what format. See the full explanation below for the reasoning.

Question

Which of the following would be done once the Project Board have authorized initiation?

Options

  • ACreate the initiation Stage Plan
  • BEstablish who needs information, when and in what format
  • CEstablish the quality expectations of the customer
  • DDefine how the project will deliver the chosen business solution

How the community answered

(39 responses)
  • A
    15% (6)
  • B
    72% (28)
  • C
    8% (3)
  • D
    5% (2)