Which is NOT an objective of the Directing a Project process?

The correct answer is C. Ensure there is a common understanding of the reasons for doing the project. See the full explanation below for the reasoning.

Question

Which is NOT an objective of the Directing a Project process?

Options

  • AEnsure the plans for realizing the post-project benefits are managed and reviewed
  • BProvide corporate or programme management with an interface to the project
  • CEnsure there is a common understanding of the reasons for doing the project
  • DEnsure there is authority to close the project

How the community answered

(13 responses)
  • A
    8% (1)
  • B
    8% (1)
  • C
    69% (9)
  • D
    15% (2)