Question

What is NOT an objective of the Directing a Project process?

Options

  • AEnsure there is authority to deliver the project's products
  • BEnsure that corporate or programme management has an interface to the project
  • CProvide sufficient information to enable the continuing viability of the project to be assessed
  • DManagement direction and control are provided throughout the project's life