nerdexam
EXIN

PR2F · Question #344

Which role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?

The correct answer is C. Change Authority. See the full explanation below for the reasoning.

Question

Which role has a specific responsibility for referring to the Project Board if any delegated limits of authority or allocated change budget are forecast to be exceeded?

Options

  • ATeam Manager
  • BProject Assurance
  • CChange Authority
  • DProject Manager

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    77% (20)
  • D
    15% (4)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice