EXIN
PR2F · Question #339
Which role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?
The correct answer is B. Project Assurance. See the full explanation below for the reasoning.
Question
Which role has a specific responsibility for checking that the project remains aligned to the corporate or programme strategy?
Options
- AProject Manager
- BProject Assurance
- CSenior User
- DSenior Supplier
How the community answered
(27 responses)- A4% (1)
- B85% (23)
- C4% (1)
- D7% (2)
Community Discussion