PR2F · Question #337
Which is a specific responsibility of Project Assurance?
The correct answer is C. Reporting highlights to the Project Board. See the full explanation below for the reasoning.
Question
Which is a specific responsibility of Project Assurance?
Options
- AApproving the Risk Management Strategy
- BGiving ad-hoc direction to the Project Manager
- CReporting highlights to the Project Board
- DEnsuring the right people are planned to be involved in quality inspection
How the community answered
(25 responses)- A4% (1)
- B12% (3)
- C76% (19)
- D8% (2)