PR2F · Question #337

Which is a specific responsibility of Project Assurance?

The correct answer is C. Reporting highlights to the Project Board. See the full explanation below for the reasoning.

Question

Which is a specific responsibility of Project Assurance?

Options

  • AApproving the Risk Management Strategy
  • BGiving ad-hoc direction to the Project Manager
  • CReporting highlights to the Project Board
  • DEnsuring the right people are planned to be involved in quality inspection

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    76% (19)
  • D
    8% (2)