Which of the following would be used to pay for an issue which would increase scope and possibly any related analysis costs?
The correct answer is C. Change budget. See the full explanation below for the reasoning.
Question
Which of the following would be used to pay for an issue which would increase scope and possibly any related analysis costs?
Options
- AContingency
- BTolerance
- CChange budget
- DRisk budget
How the community answered
(39 responses)- A8% (3)
- B5% (2)
- C72% (28)
- D15% (6)