nerdexam
EXIN

PR2F · Question #31

Which statement describes risk cause?

The correct answer is B. The situation or event that gave rise to a risk. See the full explanation below for the reasoning.

Question

Which statement describes risk cause?

Options

  • AThe impact of a risk on the stage and project tolerance
  • BThe situation or event that gave rise to a risk
  • CThe area of uncertainty in terms of the threat or opportunity
  • DHow likely a risk is to occur in a given project situation

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    82% (42)
  • C
    10% (5)
  • D
    6% (3)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice