Which of the following is a request for change?

The correct answer is D. Although it has passed quality control, a user would like to suggest an increase in the durability of. See the full explanation below for the reasoning.

Question

Which of the following is a request for change?

Options

  • AThe Executive feels that the project product may not be of sufficient quality in order to achieve the
  • BThe Project Manager has been advised that a team member has been taken ill and so the end
  • CThe supplier needs to amend a product because it does not conform to its quality criteria
  • DAlthough it has passed quality control, a user would like to suggest an increase in the durability of

How the community answered

(34 responses)
  • A
    18% (6)
  • B
    3% (1)
  • C
    6% (2)
  • D
    74% (25)