EXIN
PR2F · Question #28
Which of the following are uses of the Risk Register during the Controlling a Stage process? 1. Obtain details on risks to include in a Highlight Report 2. Obtain details of risks that may affect…
The correct answer is C. 1, 3, 4. See the full explanation below for the reasoning.
Question
Which of the following are uses of the Risk Register during the Controlling a Stage process? 1. Obtain details on risks to include in a Highlight Report 2. Obtain details of risks that may affect the Stage Plan for the next stage 3. Capture uncertainties identified when authorizing a Work Package 4. Obtain details of any potential impacts that may affect the Business Case while reviewing the stage status
Options
- A1, 2, 3
- B1, 2, 4
- C1, 3, 4
- D2, 3, 4
How the community answered
(52 responses)- A4% (2)
- B8% (4)
- C73% (38)
- D15% (8)
Community Discussion
No community discussion yet for this question.