If, at the end of each stage, circumstances external to the project had changed which affect the project's costs, risks and benefits, which product should be updated to reflect this?
The correct answer is B. Project Plan. See the full explanation below for the reasoning.
Question
If, at the end of each stage, circumstances external to the project had changed which affect the project's costs, risks and benefits, which product should be updated to reflect this?
Options
- AException Plan
- BProject Plan
- CProject Brief
- DBusiness Case
How the community answered
(33 responses)- A6% (2)
- B79% (26)
- C12% (4)
- D3% (1)