Which of these statements is FALSE?
The correct answer is C. A PRINCE2 project may have only activities, i.e. no products. See the full explanation below for the reasoning.
Question
Which of these statements is FALSE?
Options
- AA PRINCE2TM project has a finite life span
- BA PRINCE2 project has a defined amount of resources
- CA PRINCE2 project may have only activities, i.e. no products
- DA PRINCE2 project has an organisation structure with defined responsibilities, to manage the
How the community answered
(48 responses)- A15% (7)
- B10% (5)
- C71% (34)
- D4% (2)