PR2F · Question #238

Which of these statements is FALSE?

The correct answer is C. A PRINCE2 project may have only activities, i.e. no products. See the full explanation below for the reasoning.

Question

Which of these statements is FALSE?

Options

  • AA PRINCE2TM project has a finite life span
  • BA PRINCE2 project has a defined amount of resources
  • CA PRINCE2 project may have only activities, i.e. no products
  • DA PRINCE2 project has an organisation structure with defined responsibilities, to manage the