How often does PRINCE2 recommend that open Project Issues should be reviewed?

The correct answer is D. On a regular basis. See the full explanation below for the reasoning.

Question

How often does PRINCE2 recommend that open Project Issues should be reviewed?

Options

  • AWeekly
  • BAt Exception Assessments
  • CAt Checkpoint Meetings
  • DOn a regular basis

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    10% (3)
  • D
    84% (26)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice