PR2F · Question #230

What is the first job carried out on receipt of a new Project Issue?

The correct answer is B. Logging. See the full explanation below for the reasoning.

Question

What is the first job carried out on receipt of a new Project Issue?

Options

  • AAllocation of priority
  • BLogging
  • CDecision on what type of issue
  • DImpact Analysis

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    75% (18)
  • C
    8% (2)
  • D
    13% (3)