Which of the following would be carried out during the Starting Up a Project process?
The correct answer is C. Appoint individuals to carry out the work required in project initiation. See the full explanation below for the reasoning.
Question
Which of the following would be carried out during the Starting Up a Project process?
Options
- AEstablish the procedure for identifying and managing risks during the project
- BCreate a detailed Business Case
- CAppoint individuals to carry out the work required in project initiation
- DEnsure that plans for realizing the post-project benefits are managed and reviewed
How the community answered
(40 responses)- A8% (3)
- B5% (2)
- C70% (28)
- D18% (7)