nerdexam
EXIN

PR2F · Question #226

Which of the following would be carried out during the Starting Up a Project process?

The correct answer is C. Appoint individuals to carry out the work required in project initiation. See the full explanation below for the reasoning.

Question

Which of the following would be carried out during the Starting Up a Project process?

Options

  • AEstablish the procedure for identifying and managing risks during the project
  • BCreate a detailed Business Case
  • CAppoint individuals to carry out the work required in project initiation
  • DEnsure that plans for realizing the post-project benefits are managed and reviewed

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    5% (2)
  • C
    70% (28)
  • D
    18% (7)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice