Please refer to section 12.2 in the PRINCE2 Manual. (The initiation Stage Plan is produced in the Starting up a Project process and is then used by the Project Board to authorize the initiation stage)

The correct answer is B. Before the Project Board authorize the initiation of the project. See the full explanation below for the reasoning.

Question

Please refer to section 12.2 in the PRINCE2 Manual. (The initiation Stage Plan is produced in the Starting up a Project process and is then used by the Project Board to authorize the initiation stage)

Options

  • AImmediately prior to the authority to deliver a project has been given
  • BBefore the Project Board authorize the initiation of the project
  • CAfter the Project Plan has been produced
  • DDuring Managing a Stage Boundary process

How the community answered

(28 responses)
  • A
    14% (4)
  • B
    79% (22)
  • C
    4% (1)
  • D
    4% (1)