PR2F · Question #22
The outputs from a PRINCE2 project are considered to be what?
The correct answer is B. Any of its tangible or intangible specialist products. See the full explanation below for the reasoning.
Question
The outputs from a PRINCE2 project are considered to be what?
Options
- AThe business benefits
- BAny of its tangible or intangible specialist products
- CIts Resources
- DThe results of change
How the community answered
(24 responses)- A13% (3)
- B71% (17)
- C13% (3)
- D4% (1)