Question

What is a purpose of the Initiating a Project process?

Options

  • ADelegate day-to-day management of the project to the Project Manager
  • BAnswer the question: do we have a viable and worthwhile project?
  • CUnderstand the work that needs to be done to deliver the project's products before committing to
  • DEnable the Project Board to be provided with sufficient information so that it can review the