When is the Risk Register created?
The correct answer is B. During the initiation stage. See the full explanation below for the reasoning.
Question
When is the Risk Register created?
Options
- ADuring the first End Stage Assessment
- BDuring the initiation stage
- CWhen preparing a Project Brief during pre-project work
- DWhen authorizing the project
How the community answered
(26 responses)- A15% (4)
- B73% (19)
- C4% (1)
- D8% (2)