When is the Risk Management Strategy produced?
The correct answer is A. After authorization has been given to proceed with the initiation stage. See the full explanation below for the reasoning.
Question
When is the Risk Management Strategy produced?
Options
- AAfter authorization has been given to proceed with the initiation stage
- BBefore the planning of the initiation stage
- CAs soon as the Project Manager has been appointed at start-up
- DAfter the Project Board have approved the Project Initiation Documentation
How the community answered
(17 responses)- A82% (14)
- B12% (2)
- D6% (1)