nerdexam
EXIN

PR2F · Question #192

If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that's been made?

The correct answer is B. Stage Plan. See the full explanation below for the reasoning.

Question

If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that's been made?

Options

  • ACheckpoint Report
  • BStage Plan
  • CBenefits Review Plan
  • DProject Plan

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    77% (24)
  • C
    13% (4)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice