If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that's been made?
The correct answer is B. Stage Plan. See the full explanation below for the reasoning.
Question
If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that's been made?
Options
- ACheckpoint Report
- BStage Plan
- CBenefits Review Plan
- DProject Plan
How the community answered
(31 responses)- A6% (2)
- B77% (24)
- C13% (4)
- D3% (1)