EXIN
PR2F · Question #190
According to PRINCE2, which of the following statements is FALSE regarding project closure?
The correct answer is C. A clear end to the project enables the organization to understand the work that needs to be done. See the full explanation below for the reasoning.
Question
According to PRINCE2, which of the following statements is FALSE regarding project closure?
Options
- AA clear end to the project gives recognition that the original objectives have been met
- BA clear end to the project provides an opportunity to ensure that all unachieved goals and
- CA clear end to the project enables the organization to understand the work that needs to be done
- DA clear end to the project transfers ownership of the products to the customer
How the community answered
(22 responses)- A5% (1)
- B14% (3)
- C77% (17)
- D5% (1)
Community Discussion
No community discussion yet for this question.