Identify the missing words from the following sentence... It is a PRINCE2 principle that a project must have justification?

The correct answer is B. Continued business. See the full explanation below for the reasoning.

Question

Identify the missing words from the following sentence... It is a PRINCE2 principle that a project must have justification?

Options

  • ASenior manager
  • BContinued business
  • CConsistent user
  • DBusiness operational

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    74% (28)
  • C
    16% (6)
  • D
    5% (2)