What does PRINCE2TM say must drive the project?
The correct answer is D. The Business Case. See the full explanation below for the reasoning.
Question
What does PRINCE2TM say must drive the project?
Options
- AThe Project Mandate
- BThe Project Initiation Document
- CThe Project Brief
- DThe Business Case
How the community answered
(40 responses)- A18% (7)
- B3% (1)
- C8% (3)
- D73% (29)