Which of the following products is NOT created during the PRINCE2TM process model?
The correct answer is B. Project Mandate. See the full explanation below for the reasoning.
Question
Which of the following products is NOT created during the PRINCE2TM process model?
Options
- AProject Brief
- BProject Mandate
- CProject Initiation Document
- DProject Plan
How the community answered
(32 responses)- A3% (1)
- B78% (25)
- C13% (4)
- D6% (2)