Question
If the Project Board wish to ensure the Communications Management Strategy covers all the stakeholders requirements for the next stage, which project management team role may they appoint to check this for them?
Options
- AProject Assurance
- BProject Support
- CProject Manager
- DQuality Assurance
How the community answered
(33 responses)- A79% (26)
- B12% (4)
- C3% (1)
- D6% (2)