nerdexam
EXIN

PR2F · Question #142

Who determines the use of a change authority and change budget during project initiation?

The correct answer is A. Project Board. See the full explanation below for the reasoning.

Question

Who determines the use of a change authority and change budget during project initiation?

Options

  • AProject Board
  • BSenior User
  • CProject Manager
  • DCorporate or Programme Management

How the community answered

(54 responses)
  • A
    78% (42)
  • B
    13% (7)
  • C
    4% (2)
  • D
    6% (3)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice