Who determines the use of a change authority and change budget during project initiation?
The correct answer is A. Project Board. See the full explanation below for the reasoning.
Question
Who determines the use of a change authority and change budget during project initiation?
Options
- AProject Board
- BSenior User
- CProject Manager
- DCorporate or Programme Management
How the community answered
(54 responses)- A78% (42)
- B13% (7)
- C4% (2)
- D6% (3)