PR2F · Question #120
Which of the following are tasks carried out as part of product-based planning? 1. Write a Project Product Description. 2. Identify activities and dependencies 3. Create a product breakdown…
The correct answer is A. 1,3,4. See the full explanation below for the reasoning.
Question
Which of the following are tasks carried out as part of product-based planning? 1. Write a Project Product Description. 2. Identify activities and dependencies 3. Create a product breakdown structure. 4. Create a product flow diagram
Options
- A1,3,4
- B1,2,3
- C2,3,4
- D1,2,4
How the community answered
(35 responses)- A71% (25)
- B3% (1)
- C17% (6)
- D9% (3)