nerdexam
EXIN

PR2F · Question #116

A stakeholder wishing to make an observation about the project would do what?

The correct answer is B. Raise an issue. See the full explanation below for the reasoning.

Question

A stakeholder wishing to make an observation about the project would do what?

Options

  • AAsk for it to be included in the Communication Management Strategy
  • BRaise an issue
  • CMake an entry in the Issue Register
  • DArrange a meeting with a Project Board member

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    76% (22)
  • C
    3% (1)
  • D
    14% (4)

Community Discussion

No community discussion yet for this question.

Full PR2F Practice