The correct answer is D. When reviewing how a stage is progressing. See the full explanation below for the reasoning.
Question
When would the Team Manager be required to produce a Checkpoint Report?
Options
- AWhen a Work Package is being negotiated
- BAt the frequency agreed in the Work Package
- COn completion of the quality-checking activities for each product
- DWhen reviewing how a stage is progressing