PMP · Question #835
PMP Question #835: Real Exam Question with Answer & Explanation
The correct answer is D: Consult the project team to understand the extent of the training needs for the contractor.. To address a contractor's lack of agile experience, the project manager should first consult the project team to assess specific training needs.
Question
A project manager has recently been assigned to an agile project and discovers that a contractor for the project does not have any experience with agile. What should the project manager do?
Options
- AAsk the project sponsor to replace the contractor since they do not have agile experience
- BIssue a formal notice to the contractor to obtain an agile certification.
- CInstruct the contractor to receive agile training since the project has already started.
- DConsult the project team to understand the extent of the training needs for the contractor.
Explanation
To address a contractor's lack of agile experience, the project manager should first consult the project team to assess specific training needs.
Common mistakes.
- A. Replacing a contractor is an extreme measure that could cause delays and cost increases, and should not be the first action.
- B. Issuing a formal notice for certification is prescriptive and may not address the practical skills needed; formal certifications aren't always a direct measure of practical agile experience.
- C. Instructing training without understanding specific needs might lead to inefficient or irrelevant training.
Concept tested. Assessing team training needs in agile projects
Reference. https://agilemanifesto.org/principles.html