PMP · Question #769

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated…

The correct answer is D. Organize a team meeting to inform team members about a change in direction and work with. To reassign tasks effectively without demotivating team members in a hierarchical environment, the project manager should communicate transparently and collaboratively.

Submitted by naveen.iyer· Apr 18, 2026People

Question

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees. What should the project manager do?

Options

  • AOrganize a team meeting and inform the team members that, as the person accountable for
  • BAsk the more experienced team member privately to take the task and inform the other team
  • CAsk the less experienced team member privately to stop working on the task and inform another
  • DOrganize a team meeting to inform team members about a change in direction and work with

How the community answered

(25 responses)
  • A
    24% (6)
  • B
    12% (3)
  • C
    4% (1)
  • D
    60% (15)

Why each option

To reassign tasks effectively without demotivating team members in a hierarchical environment, the project manager should communicate transparently and collaboratively.

AOrganize a team meeting and inform the team members that, as the person accountable for

Informing the team in a top-down manner about task reassignments, even from an accountability standpoint, can be perceived negatively and may not foster buy-in or address concerns about performance.

BAsk the more experienced team member privately to take the task and inform the other team

Asking team members privately to take or stop tasks, then informing others, lacks transparency and can lead to resentment, distrust, and negative team dynamics.

CAsk the less experienced team member privately to stop working on the task and inform another

Handling task reassignments privately and without open discussion can create a perception of unfairness and negatively impact team morale, particularly in a task-completion-focused environment.

DOrganize a team meeting to inform team members about a change in direction and work withCorrect

Organizing a team meeting to openly discuss a change in project direction and collaboratively work with the team to reassign tasks fosters transparency, builds consensus, and mitigates the perception of poor individual performance. This approach respects the team while ensuring project milestones are met by involving them in the solution.

Concept tested: Team leadership, communication, and change management

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Team Leadership#Communication Management#Conflict Management#Change Management

Community Discussion

5
Luis F.Luis F.Feb 19, 2026

D is the one. In a hierarchical org where people stress over task completion metrics, you gotta be transparent about the change in direction and collaborate with the team so nobody feels singled out or penalized.

23
Carlos M.Carlos M.Feb 10, 2026

D is right but man that option text cuts off mid-sentence. A is tempting because in a hierarchical org just pulling rank feels natural, but the key is working with the team on the change, not just dictating it.

4
Samuel O.Samuel O.Feb 12, 2026

D is the right call here. In a hierarchical environment where people are evaluated on task completion, you have to be transparent about the change in direction so nobody thinks their performance is being questioned, and working with the team on the reassignment shows leadership rather than just issuing orders.

1
Luis F.Luis F.Feb 13, 2026

Agreed on D, Samuel, the transparency piece is huge so nobody panics about their metrics, and I would add that documenting the rationale for the reassignment helps cover everyone if management asks why priorities shifted.

0
Bao N.Bao N.Jan 26, 2026

D on this one. The stem screams collaborative leadership since you are in a hierarchical culture and need to avoid making people feel demoted, but I am curious whether the exam always expects a team meeting over a private one on one when the reassignment involves only two people.

-2